Curb and asphalt removal have started in the east half of the project area. Curb pouring in prepped areas is scheduled to begin this week. Blacktop repair will follow once the concrete used for curbing has properly cured.
If Your Curb Has Been Removed in Front of Your Driveway
- You will temporarily have limited, or no access to your driveway.
- Curb will be repaired/replaced.
- Blacktop will be repaired/replaced.
- Once both curb and blacktop repairs have been completed, homeowners can have full-access to their driveways.
Work being done east of Jansen Ave NE should be close to completion by the end of this week. Public Works crews will then move to the west area of the project to start curb removals, drainage improvements, and curb/blacktop repair.
The goal for completion is mid- to late-July.
Reminder...
All work is weather dependent and has already had an impact on the project's work schedule.
Questions?
Call Public Works Supervisor Pat Sele at 763-416-7981.