Project Schedule

 

Timeline

  • 2024: Feasibility study and public hearings
    • Aug. 14, 2024 | Neighborhood Open House
    • Oct. 8, 2024 | Order Feasibility Study
    • Nov. 12, 2024 | Accept Feasibility Report, Set Public Hearing
    • Nov. 26, 2024 | Public Improvement Hearing/Order Final Plans
  • Early 2025: Final designs and bidding
    • Feb. 11, 2025 | Approve Plans and Specifications/Authorize Ad for Bid
    • March 7, 2025 | Bid Letting
    • March 11, 2025 | Receive Bids/Order Assessment Hearing
    • April 8, 2025 | Assessment Hearing/Award Construction Contract
  • May 2025: Construction begins
  • October 2025: Project completion

 

This schedule is subject to change